Skip to content
DNMControls &
Automation

Service

Machine retrofit and plant upgrade

The plant already exists. It runs, it makes money, and the controller inside it went out of production nine years ago. This is the work we are built for.

Photograph pending · 3:2The 'before' of a retrofit — an ageing panel with obsolete hardware, dusty, as found on sitepublic/photography/legacy-panel-before.jpg

A retrofit is a different discipline from a new build. On a greenfield project the risk is that you finish late. On a retrofit the risk is that the plant does not restart, and that risk is carried by production, not by the project.

So the planning is inverted. We start from the shutdown window you can actually give us and work backwards, doing as much as possible while the plant is still running: new panel built and tested off-line, new controller programmed and simulated, cabling pre-run and pre-labelled. The window itself gets used for the changeover, not for engineering.

Migration paths we run regularly

FromToThe part people underestimate
Allen Bradley PLC-5 / SLC-500ControlLogix or CompactLogixInstruction behaviour differs; direct conversion output needs reviewing line by line.
Allen BradleySiemens S7-1500A rewrite, not a conversion. The value is in restructuring the logic while it is open.
Siemens S7-300 / S7-400S7-1500 (TIA Portal)Rack and I/O addressing changes, and old STEP 7 blocks rarely port cleanly.
WinCC FlexibleWinCC Unified / AdvancedScreens and scripts are rebuilt. Treat as new development.
Obsolete VFDsCurrent SINAMICS / PowerFlex / Altivar / VLTMechanical fit and cable gland positions, not the drive parameters.
Relay logicPLC controlNobody has documented the actual sequence in twenty years. Recovering it is most of the job.
Photograph pending · 3:2The same machine or plant area after DNM's retrofit — new panel in place, same framing as the 'before'public/photography/retrofit-after.jpg
Before and after on the same machine, shot from the same position. The plant ran through the following shift.

How we plan a changeover

  1. Step 01

    As-found survey

    What is actually installed, not what the drawings say. Photographs, I/O count, network topology, spares held, licence position, backup state.

  2. Step 02

    Migration path and risk register

    The recommended target platform, what it costs, what it does not fix, and what could go wrong on the night with a named mitigation against each item.

  3. Step 03

    Off-line build and proving

    New panel built and FAT-tested, new program written and simulated, screens developed — all while the plant runs.

  4. Step 04

    Rollback proved

    The old system stays intact and restorable until the new one has run production. A rollback plan that has not been tested is not a rollback plan.

  5. Step 05

    The window

    Hour by hour, agreed with production, with a defined abort point past which we go back rather than push on.

  6. Step 06

    Restart and watch

    An engineer stays on site through the first production runs. Hand-back is a decision, not a date.

Why a small team wins this work

Retrofit rewards senior engineers who can make a decision at 2am on the plant floor. It punishes large project structures where the person on site has to phone somebody to approve a change. That is the whole of our advantage here, and it is why we lead with this service rather than greenfield mega-projects.

Questions we get asked

Next step

Have a machine retrofit & plant upgrade enquiry?

Send the plant detail — platform, I/O count, what has gone wrong, and the window you can give us. An engineer picks it up.

An engineer responds within one business day.

CallWhatsAppQuote